Dehradun – In a high‑level Executive Committee meeting at the Secretariat, Chief Secretary Anand Bardhan examined the status of multiple Uttarakhand Investment and Infrastructure Development Board (UIIDB) initiatives. He warned that every scheme must adhere to its sanctioned schedule and that progress reviews should be systematic and rigorous.
Sharda Riverfront Corridor Gets a Dedicated Manager
The Chief Secretary voiced frustration over the sluggish pace of the Sharda Riverfront Corridor, noting that the implementing agency, UPDCC, had achieved merely about 10 % of the work after ten months. To accelerate delivery, Bardhan ordered the appointment of a full‑time project manager on site, tasked with continuous monitoring and swift issue resolution.
He also instructed the preparation of PERT charts for all UIIDB projects, embedding clear milestones. Each meeting will now benchmark progress against these charts, and any lag will trigger root‑cause analysis and corrective action.
River‑Rafting Ventures Receive New Oversight
Projects aimed at expanding river‑rafting facilities were also reviewed. Bardhan directed UPDCC to form a dedicated five‑year team responsible for the operation and maintenance of these attractions.
Separate operational units are to be set up for the Haridwar and Rishikesh corridors, ensuring smooth, localized management of the rafting infrastructure.
Priority Works Targeted for Kumbh Mela 2027
With the Kumbh Mela slated for 2027, the Chief Secretary emphasized that all priority constructions must meet their deadlines. For the Sati Kund works, he ordered an increase in labor strength and shift rotations so the project can be wrapped up by 15 December, while cautioning that speed must not erode quality.
In Haridwar, the general manager of the executing agency has been instructed to reside in the city and conduct daily site inspections. A detailed progress dossier must be forwarded to the District Magistrate and the Divisional Commissioner on a regular basis.
Clear Protocols for New Parking Facilities
Before embarking on any new surface, underground, or mechanical parking scheme in Haridwar, officials must secure a written No‑Objection Certificate from both the District Magistrate and the Mela Officer.
Integration with parallel departmental plans is mandatory, and the choice of parking solution should reflect local demand—opting for the most practical configuration among surface, underground, or automated systems.
Financial & Audit Committee to Guard Project Funds
Bardhan also mandated the creation of a Financial and Audit Committee to tighten fiscal oversight of UIIDB undertakings. The committee will champion financial discipline, transparency, and timely disbursement across the board.
Present at the meeting were Principal Secretary R. Meenakshi Sundaram, Secretary Nitesh Kumar Jha, Ravinath Raman, Dr. Pankaj Kumar Pandey, C. Ravishankar, Dr. Ranveer Singh Chauhan, Special Secretary Parag Madhukar Dhakate, along with senior officials from the relevant departments and UIIDB.